Line Nme:Reconductoring of Confidence 113 MW Power Plant to Rangpur 132kV Double Circuit Transmission Line
-
Total Length: 10353.24 km
- CKT-1 Energized
- CKT-2 under progress
We have already started work on another line. confidence 113 MW power plant to rongpur 132 kv DC TL
- Section- AP150 To AP127 CKT-1 New conductor installing done & Energized 02 Jun 2025 Time:02:25PM
- Our work has resumed after Eid. 16 Jun 2025
- Shutdown recevied 17 Jun 2025 CKT-2
- Rongpur S.S To Rongpur Confidence S.S CKT-2 work going on
And we think we will complete this work very quickly with 100% safety and security.